| | | | | | | | JuneĀ 18, 2019 Board Meeting Agenda Item 41.
|
| | | | | | | | Title APPROVAL OF CONSTRUCTION MANAGER RANKINGS FOR THE ENGLEWOOD ELEMENTARY SCHOOL BUILDING #6 PROJECT
Description The project's scope of work shall include construction management services for the demolition and construction of a replacement classroom wing (Building #6). On 5/29/2019, the Professional Services Selection Committee (PSSC) met to select a construction manager for this project. The PSSC has ranked them in accordance with School Board policy #7.71. The preliminary project budget is $5,500,000.00. Funds for this project are available in the capital budget account.
Recommendation That the rankings of Construction Manager for the Englewood Elementary School Building #6 Replacement project be accepted as presented and the Director of Construction Services be authorized to attempt negotiations with the top-ranked firm.
Contact MAULTSBY & SMITH
Financial Impact $5,500,000.00 |
|