Item Coversheet

Sarasota County Schools Logo
JuneĀ 18, 2019 Board Meeting
Agenda Item 37.

Title
ACCEPTANCE OF FACILITIES SERVICES' PROJECT COMPLETION AND APPROVAL OF THE FINAL PAYMENT TO CONTRACTOR FOR THE TRIAD NORTH COUNTY SCHOOL, SECURITY UPGRADES AND FENCING (DESIGN & PRECONSTRUCTION) CONTRACT

Description
The final project costs have been internally audited and are enclosed herein the final payment application #02 to the contractor for approval. The Executive Director of Facilities Services has determined that the project is complete in accordance with state statutes. Being this is a design and preconstruction only contract, a certificate of substantial completion is not needed.

Recommendation
That the project be accepted as complete and the final payment to contractor be approved as presented.


Contact
MAULTSBY & DUMAS

Financial Impact
N/A
ATTACHMENTS:
DescriptionUpload DateType
21901929-2-FINAL 5/31/2019Cover Memo