ACCEPTANCE OF FACILITIES SERVICES’ PROJECT COMPLETION AND APPROVAL OF THE FINAL PAYMENT TO THE CONTRACTOR AND THE CERTIFICATE OF SUBSTANTIAL COMPLETION FOR THE BOOKER MIDDLE SCHOOL CLASSROOMS OF TOMORROW (COT) LABS SUMMER 2023 CONTRACT

Description

All work has been completed and all required close-out documents have been received from the contractor. The final project costs have been internally audited, and the final payment application and backup #22303569-02 are enclosed. The Director of Facilities Services has determined that the project is complete in accordance with state statutes.



Gap Analysis

COT Labs are part of an ongoing project whereas a few Labs are added on a yearly basis.



Previous Outcomes 

All additions are done on an as needed basis and there are quite a few of “unforeseen” conditions which we ask the General Contractor to cover with a contingency, so we do not have unexpected budget. As it is, this project was pretty straight forward which resulted in a change order returning the contingency to the district and final payment to the General Contractor as reflected in this amount.



Expected Outcomes 

All monies unused will be returned to the district and monies owed to the General Contractor will be paid to them.



Strategic Plan Goal

Recommendation

That the project be accepted as complete, and the final payment and certificate of substantial completion be approved as presented.



Contact Information

DON HAMPTON   don.hampton@sarasotacountyschools.net 

JODY DUMAS   jody.dumas@sarasotacountyschools.net



Financial Impact

N/A



ATTACHMENTS:
DescriptionUpload DateType
FAC Nov 28 BMS COT Labs Final 11/8/2023Cover Memo