| | | | | | | |  October 15, 2024 Board Meeting Agenda Item 16.
|
| | | | | | | | Title APPROVAL OF CONSTRUCTION MANAGER CONTRACT FOR CONSTRUCTION SERVICES FOR THE VENICE HIGH SCHOOL STADIUM ENHANCEMENTS PROJECT
Description Under the terms of the 5/21/2024 (Item #25), Board approved "Agreement between Owner and Construction Manager for Preconstruction, included preconstruction services only. The project's scope of work includes but not limited to the design and construction of additional restrooms, football field turf, concession renovations and/or replacements, security enhancements, bleachers, baseball netting and sand volleyball courts. On 9/24/2024, the Director of Construction Services and a member of the Professional Services Selection Committee (PSSC) met with Gilbane Building Company and have successfully negotiated a construction contract. The amount of this contract, for construction services, is $11,203,887.00. The total project budget is $12,300,000.00
Gap Analysis In order to begin the construction services for the Venice High School Stadium Enhancements project, the construction manager's contract must be submitted for Board approval.
Previous Outcomes The Board approved the construction manager's preconstruction contract on 5/21/2024, which authorized staff to negotiate construction services.
Expected Outcomes Execution of this contract will allow the construction services for the Venice High School Stadium Enhancements project to commence.
Strategic Plan Goal
Pillar 4 - Every School Equipped
Priority 2 - Create High Quality Infrastructure Recommendation That the construction manager contract with Gilbane Building Company for the Venice High School Stadium Enhancements project be approved as presented.
Contact Information
JANE DREGER jane.dreger@sarasotacountyschools.net
JODY DUMAS jody.dumas@sarasotacountyschools.net
MICHAEL KEMP michael.kemp@sarasotacountyschools.net
Financial Impact
$11,203,887.00, which is included in the total project budget
Funding Source: Capital
|
|